|
New Ipswich Congregational Church |
|
Thank you to Jim Cooper and Steve Eaton for all their numerous hours, up to 30 hours per week, in being instrumental in returning us to our Meeting House. We appreciate all the contractors who have assisted us. We thank the many volunteers who spent countless hours painting, moving furniture, staining, repairing and praying for the completion of this daunting task.
Feb 16th, 2008
August 2008 As we get prepared to move back to the Meeting House that has
undergone a transformation of giant proportions, it is important to remember all
the work that has gone into this project. First we are reminded of the
charge given to the Building Committee by the Executive Ministry Team and the
appointment of members to the Building Committee. (See below) We believe
that we, as a Building Committee, were diligent in our work in fulfilling the
charge as there were a lot of tasks to undertake before we could get to the
rebuilding stage. We believe that we, as a committee, covered every topic
in detail so that there would be no stone unturned. We also believe that
after meeting with engineers, architects and experts on wood structures that the
decisions made by this committee were in accordance with our charge. NICC Building Committee Charge The Executive Committee of NICC appoints this Building Committee for the following purpose: To investigate short term solutions to the building problems
identified by structural engineers, Kimball Chase, and in a timely manner to
bring to the membership for their vote the most feasible solution along with
associated costs.
The work detail to get the tiles out of the way so they can grind the basement floor has been completed. The pews have been relocated to the back classrooms so that we can start working, repairing and reassembling them. The upper parking lot is getting patched and the trench containing the drain pipes will be capped with concrete. The upper side entry way will have a new concrete sidewalk. The tension rods in the sanctuary have been painted. The wood shingle work and painting has been completed on the exterior. As you can see a lot has been done and there is still a lot left to do. There will be announcements coming for more work details as we get closer to accomplishing our goal of getting into our Church. A great big thank you to all you have volunteered their time to help with all the various tasks and details that have to be done. The Building Committee is please to announce that our anticipated date of return to our building is the mid to end of July. Please continue to pray for our Project Managers - Steve Eaton and Jim Cooper. Their task is coming to an end, but they have a ways to go. Thank you to all who have helped with the building and the supporting families. As the song states, "We are the Church, You are the Church", but it will be good to return to our meeting house.
The building committee is excited to report that various phases
of construction are underway. I would first like to thank the finance
committee for all their work in securing financing for the project. The
roof has been completely replaced. The rough electrical and plumbing are
underway and the balcony's rough framing is being worked. The general
framing is coming along and Jim and Steve are working hard to see that
everything is on track, both physically and financially. Renovations to historic church brings building into 21st centuryPublished: Monday, February 11, 2008 By JESSIE SALISBURY, Telegraph CorrespondentNEW IPSWICH – Except for some staging and a blue plastic tarp covering the
roof, the outside of the New Ipswich Congregational Church looks as it has since
1902. However, almost all the original interior is gone.
The major change to the sanctuary will involve moving the alter from the east
to the west end and adding a balcony at the west end. The nave will be made
longer by the removal of a wall so that an additional 50 seats can be installed,
bringing the capacity to 269. The balcony will be primarily for organ and choir
but will serve as overflow seating, Cooper said.
The Building Committee is looking for some volunteers to serve on sub committees - color/lighting, sound/music, kitchen upgrade, space usage, public relations, and landscaping. If you are interested, please see on of the Building Committee members.Thank you to Jim Cooper who took many of us on a tour of the building on Saturday, January 19. It was great to see the changes and imagine the completion. Thank you to Jim Cooper and Steve Eaton for their dedication to this vision.From the Building Committee We are pleased to announce that our coordinators for the project are Jim Cooper and Steve Eaton. As you can already see they have been hard at work with the contractor making sure the building permit was in place and going over details of the project that are important to us. I have recently returned from vacation and was so excited to see the work that had begun. I got to take a first hand look at the work as Steve Curtis, Old Time Restoration, gave me a tour through the structure as it had been gutted and exposed. As of the writing of this a little over ten dumpsters had been used for the demo work. I asked about insulation in the walls and was told that there was little to none. (I am thinking about the fuel/financial savings once the new insulation is in). I was also briefed by Jim Cooper and was shown by Steve Curtis the column/support that was inside the altar wall. This support was actually cracked and bulging. (The expansion helped us uncover this problem. This column/ support will be removed to accommodate the expansion). I was also shown that the pipe for the kitchen drain was found and that it will be plumbed into the septic drain. The perimeter drainage system was going in as well as the parging (filling in of the cracks with cement) of the stack stone foundation. This will eliminate the water issues in the basement. Steve Curtis told me that the job was going well and that the communication with the coordinators was great. I hope that we will have a slide presentation soon so that everyone else can see the magnificent work that is being done. I was thinking about our up and coming event “The Light Still Shines at NICC” and can’t help but get excited and think that this project is a beacon to all to show that with God’s love and promise all things are possible and that during this Christmas Season we may all realize the gifts and blessings He bestows on us everyday and be a grateful people. Merry Christmas! The Building Committee is looking for people to sign up and volunteer time and talents for the following sub committees: See a member of the Building Committee if you are interested. There is also a request from the Funding Committee looking for new people to serve on that committee as well. See Bob Romeril if you are interested. Building Committee We would like to thank the entire congregation for their support, love and prayers over the last year. We know the process took a long time and with your patience and God’s guidance, we as a committee, were able to do the work. We feel this project that we are undertaking is a true testament of the faith and strength that this congregation has. In the weeks to come we will all see the work start to take place. During this time we need to be patient and prayerful. We would ask that any questions or comments you have during this process be directed to the building committee or trustees. We will also have periodic updates of the work in progress. Thank you for the continued support and commitment to this project and continue to pray for us during this time.
Proposed Plans for the renovation of our church building are available at the parsonage. Please contact Geri Nelson at 878-1327 to get a copy. If you would like additional information, please contact Mark Krook at 878-1327 |
Send mail to
info@ni-cc.org or call 603-878-1327 with
questions or comments about this web site.
|